Hello Experts,
Recently we did a EHPI of our ABAP BW system from 7,0 ABAP- 7.01 BW ABAP System.
However for the Portal Java we have kept at NW 7.0 SP25 According to SAP Note 1163789 - NetWeaver 7.0: BI Java Synchronized Patch Delivery Strategy
The note says
"
SAP recommends to have the ABAP and Java parts of the server on the same Support Package Stack level. For BI, however, the tight dependency between ABAP and Java Support Package Stacks, which had to be updated in parallel, no longer exists. The BI-specific Patches can be applied compatibly to a different Support Package Stack. Note that this is not true for upgrades (like for instance from Netweaver 7.0 to 7.1), it only applies within the same release and enhancement package level. "
However when I run a SAP Diagnostic support desk tool according to SAP Note 937697" , it says not compatible.
My Question is , is it compatible to have a BI 7.0 Java SP25 and BW ABAP on 701 SP10?, According to Synchronized Patch delivery , it says compatible.
Your thoughts on the same please.
Kind Regards,
Jacob