Hello everyone,
I'm planning a BW upgrade from release 7.0 to 7.31 (ABAP Only). The system has the following components:
BI_CONT - version 7.04
PI_BASIS - version 2005_1_700
SAP_ABA - version 7.00
SAP_BASIS - version 7.00
SAP_BW - version 7.00
Plus:
FINBASIS - version 6.00
SEM-BW - version 6.00
Plus ST-A/PI and ST-PI
My questions are the following:
1) As the system has FINBASIS + SEM BW, can it be upgraded in one step to 7.31 with SUM?
2) The system is still using the authorizations from BW 3.5, Do I have to update the authorizations to BI 7.0 before the upgrade? or It can be done after the upgrade? Which is the best approach?
3) If the sw componetns FINBASIS and SEM-BW are upgraded in BW system, Does the ERP has to be upgraded too?
Regards,
JAM